Previous Page  29 / 116 Next Page
Information
Show Menu
Previous Page 29 / 116 Next Page
Page Background

www. e l e c t r i c a l c o n n e c t i o n . c om . a u

29

and experiences of RAN servicemen and

women will be remembered and shared

with future generations.

“We are well aware of the significance

that this building holds within the

community. Over half a million people,

including 50,000 school children, visit the

pavilion each year to learn about the role

of the RAN during and following World

War I,” he says.

“The pavilion has become a permanent

tribute to the men and women of the RAN.”

The project itself was rife with

challenges, Josh says, including the

necessity of having a team working

under the wharf; planning around the

tidal conditions of the harbour; working

between the wharf and the vessels

to connect services; extending fibre

optic cabling and mains cabling under

the wharf; using boats to complete

installations; and, installing lightning

conductors in the water.

“When electing which of our team

members would work on this project,

we had to be certain of their abilities

and commitment to the project because

many of the installation components

were considered ‘high risk’. Suppliers

were also heavily scrutinised as any

delay in the supply of material could

prove detrimental to the completion

of the project.

“Safety was the main focus for the

Kerfoot team. Condition monitoring

and knowledge of the tides was

required for all works under the wharf

and on the water while integration with

the vessels took place.

“The Kerfoot team had to plan months

in advance with the vessel crew to

complete disconnects, alterations and

reconnects to the vessel services.”

Working from boats to install large

submains, lightning conductors and under-

wharf reticulation also required careful

planning and management as some of

the tidal conditions only allowed work

to be completed under the wharf for a

maximum of four hours a day.

“Further, Kerfoot was not the only trade

to carry out works under the wharf and

therefore coordination between trades

was a necessity.

“The busy nature of the harbour also

posed a challenge as passing ferries and

boats could cause large waves. To manage

and overcome this challenge works were

booked weeks in advance and planned

with great precision.”

Due to the inherent difficulties of

working on and near the water, the

Kerfoot team undertook CPR and

lifesaving training to ensure all team

members were aware of the risks involved

with the situation and how to respond to

an emergency.

“Large sections of the works were

completed using boats and special

working platforms elevated over the

harbour; but, the project was delivered on

time, with no safety incidents and minimal

disruption to the visitors and client.”

Technically speaking, given that the

vessels were not a permanent fixture

of the museum, disconnection from the

pavilion needed to be a simple process for

staff, Josh says.

“These vessels required 415V power,

structured cabling and a fire detection

system to be connected. The submarine

alone also required a 110V DC supply.

“The Kerfoot team engineered a

quick connection box for both vessels.

This quick connection box contained

plug-in modules for all of these services

allowing the vessels to be relocated for

maintenance and cleaning without a

major electrical shutdown.

“These boxes were designed to be

concealed in the ceiling void located just

under the gangways on the vessels.”

The brief also called for the installation

of a lightning protection system to

protect the building’s delicate facade.

Kerfoot worked with the architect to

conceal all lighting protection components

while maintaining compliance with

Australian Standards.

“Stainless steel hand railings and small

fins connected to the building were used

as lightning conductors, to minimise the

visible components. The footings were

also part of this system, which let us hide

the conductors below the deck of the

existing wharf. This made the installation

almost invisible.”

Another important aspect of the project

was to ensure that all works undertaken

on the water had no impact on the

environment. This posed a challenge when

drilling and cutting into the wharf as all

dust and debris had to be contained.

As a result, Kerfoot worked closely with

the Environment Protection Agency (EPA).

“On completion of the project the

EPA signed off on all works, meaning

that we had had no effect on the

environment,” Josh says.

In September, Kerfoot won the

Commercial – Small Project category at

the 2016 NECA NSW Excellence Awards

for its work at the pavilion.

“For Kerfoot to be recognised as a

winner not only reflects the high standard

of work our dedicated team can produce,

it also confirms our position as a top

electrical contracting and management

company within the industry,” Josh says.

“This shows our ability to adapt to any

of our client’s requirements, overcoming

environmental boundaries, however

difficult they may be.”

> Kerfoot

www.kerfoot.com.au

“Thepavilionhas become apermanent tribute to themen

andwomenof theRoyal AustralianNavy.”