Previous Page  27 / 116 Next Page
Information
Show Menu
Previous Page 27 / 116 Next Page
Page Background

www. e l e c t r i c a l c o n n e c t i o n . c om . a u

27

BY

BRIAN

SEYMOUR

in the UTS ePress article

Essence of Time in

Construction Contracts.

Abstract: The building industry has in

recent years seen huge costs incurred due

to disputes arising on notice requirement

clauses. These claims could have been

averted if the parties had been diligent

in providing the necessary notices.

This article sets out to explore the law

briefly as interpreted by the courts in

common law and equity and to discuss the

possibility of defence under the principle

of promissory estoppel.

More important, it also shares the

author’s view on how such pitfalls could

have been prevented by giving the proper

notices within the timeline required by the

contract conditions.

Numerous contractors have suffered

losses due to the head contractor’s

mismanagement of the project, including

delay, disruption, acceleration, out-of-

sequence work, stacked trades and

interference between trades.

This is a difficult issue for many

estimators, and before signing a contract

it is wise to have a qualified person review

it. It is good practice to do this before

starting an estimate, including allowances

for uncertain language used or contract

clauses that contain illegal requirements –

and to be careful about clauses that make

it impossible to profit from variations.

At common law, there is no automatic

right to delay damages. As with all

damages claims, delay damages can

be recovered only if they can be proved

to be damages resulting from a breach

of contract.

As regards a construction project,

the contractor must show that the

loss suffered arose naturally from the

principal’s breach, or may ‘reasonably

be supposed to have been in the

contemplation of both parties’ at the

time the contract was entered into. Delay

damages can be recovered automatically

only when a contract specifically allows.

Clause 34.9 of AS 4000-1997 and

AS 4902-2000 provide that, where an

extension of time has been granted, the

contractor is entitled to ‘delay damages’

for every day falling within an extension of

time for a ‘compensable cause’.

In the recent case of Adapt

Constructions Pty Ltd v Whittaker [2015]

ACTSC 188, the ACT Supreme Court found

that a construction contract based on

a standard form, which left blank the

amount for liquidated damages to be

paid for delays to completion, did not

prevent the principal to the contract

from recovering unliquidated damages at

common law for that delay.

It is difficult to prove damages. To

calculate labour losses from start-and-

stop work, double-handling of materials

and shifting of labour, such losses

are commonly categorised as loss of

efficiency, but in many ways this heading

is misleading.

It is not so much that the electricians are

inefficient while they are working, it is that

they cannot get to the work. Time is lost

waiting, being reassigned to other areas,

gaining access to work areas, and other

mobilisation and demobilisation cycles.

Also, there are real costs associated with a

loss of ‘learning curve’ and morale.

There are many factors to consider in

the selection of labour units to be used

in a competitive tender. Understanding

the effects of a particular project or

installation, and adjusting the labour units,

will determine whether you win or lose the

tender. Once you win the tender, it will also

determine whether you will be profitable.

Consider the different elements of the

project to be sure you have selected the

best labour units for the material and

application to enter in the estimate. Do

not use the same level of units for every

estimate: different parts of a project may

require different labour unit levels.

For instance, if you are installing

runs of 25mm conduit in a concrete pour

and also in a false ceiling, this would

require different labour units for the

same material.

You also have to look at repetitiveness.

Installing one run of 25mm conduit in the

concrete pour will take longer per 100m

than four parallel runs of the same conduit.

The same labour discounts apply when

installing two 600 x 600 flush lighting

fixtures in one room versus 300 of them in

an open office. You gain productivity.

Issues to consider when applying

labour units:

>

Higher ceilings increase labour.

>

Increased quantities increase productivity

and decrease labour units.

>

More parallel runs will decrease the

labour unit per 100m.

>

Equipment choices can affect labour units

– scissor lift, scaffold, cherry pickers, etc.

>

Multiple floors of a building will increase

the labour for that installation.

>

The further the material storage is from

the workface, the more walking time

must be allowed.

Other considerations include

the following:

What is the condition of the worksite,

and will there be clear access to installation

areas? Is it likely that mechanical services,

materials and equipment, or stacked

ceiling tiles will inhibit access?

How good is the head contractor at

keeping the project clean and tidy? Will

there be stacked trades at the workface?

This is why it is important to know the

head contractor you are tendering to.

How good is a particular head

contractor at keeping the project on

schedule? A project that stays on schedule

usually results in lower labour cost.

Weather has an effect on the project.

Extreme temperatures can have a

demoralising effect on productivity. When

is the site or slab work scheduled on the

project? Is it in the exhausting heat of

summer or the extreme cold of winter?

The project location will be the guide.

As one can see from the above, the

application of labour to any project cannot

be merely entered straight from the labour

units without intelligent consideration of

the contract conditions, project conditions,

and labour and material availability.