NBN Co updates short-term fibre rollout timeline
NBN Co updates short-term fibre rollout timeline
- Construction delay of about three months in decade-long project
- NBN Co takes action to assist construction contractors to meet their commitments, including assuming direct responsibility for NT fibre rollout
- Technology supply, back-end IT systems and customer processes for the fibre network all on track
- 2021 completion date and overall cost of the NBN unchanged
Some of NBN Co’s construction contractors have progressed work on the ground at a slower rate than forecast, but this delay will be recovered.
ADVERTISEMENT
The June 2013 Corporate Plan target of passing 341,000 premises with fibre is now expected to be achieved about three months later. Between 190,000 and 220,000 premises are now forecast to be passed by fibre by end June.
NBN Co chief executive Mike Quigley says, “We are accountable for the delay and are disappointed it has occurred.
“We work closely with our suppliers across all parts of our network to build and monitor their progress to ensure each individual element is ready within the required timeframe.
“In the case of the volume fibre rollout, NBN Co’s public projections have been underpinned by commitments from our four construction contractors that they would meet the 30 June target.
“The problem is we are just not seeing the ramp up of construction workers on the ground that would be needed to deliver these targets.
“This lack of mobilisation, combined with some of our contractors recently lowering their forecasts, has led us to make the judgment call to reforecast our end-of-year projections.
“That is why we have taken immediate action to address the delay.”
The actions include:
- NBN Co will directly manage the Northern Territory rollout to ensure the delivery of fast broadband to the NT and to allow contractor Syntheo to focus on WA and SA. This will see NBN Co create up to 200 jobs in the NT at the peak of the rollout
- NBN Co and its construction partners will train and employ additional specialist telecoms workers (“fibre splicers”) to help recover lost time in the rollout of the network
- NBN Co’s fibre construction contractors will increase their investment in equipment and manpower as well as technology to accelerate on-the-ground design and planning.
According to Mike, other major deliverables for the NBN’s fibre network are tracking well.
“We have more than 40 telephone and internet service providers selling NBN packages to consumers. The rollout of the transit network is on track. We are having no problems with the availability of equipment including the manufacture of fibre, and the implementation of the complex IT systems (OSS/BSS) that underpin the running of the network, also continue to be delivered as expected.
“I should be clear, this short-term issue will not affect the long-term delivery of the NBN or the overall cost of the project.
“NBN Co remains on track to deliver fast, affordable and reliable broadband to every Australian by 2021 as set out in our Corporate Plan.”
-